Departments don't take Gateway Reviews seriously enough
By Steve Ranger
Published: 5 July 2005 13:30 BST
More than a quarter of government technology projects have hit a "red light" during the review process aimed at cutting IT project failures.
And eight have hit consecutive red reviews during the Office of Government Commerce Gateway Review process, highlighting "substantial difficulties", according to a report by the Public Accounts Committee (PAC).
PAC chairman Edward Leigh said: "Far too often, major IT-enabled projects in government departments are late, well over budget, or do not work at all - an enormous waste of taxpayers' money."
The Gateway Review process was developed to provide better scrutiny of IT projects, so that potential problems can be spotted early enough for corrective action to be taken.
According to the report, by the end of March 2004, 254 IT projects had been reviewed, with 50 per cent getting an amber rating, 28 per cent red, and 22 per cent green.
A red rating means that in order to achieve success the project team should take action immediately as risks have been identified.
Of the eight that received two consecutive red reviews only one has received a subsequent green review and one an amber, with two of the others under further review.
But one in five projects have actually got worse as they progressed through the Gateway process, and two in five failed to get better, the report reveals.
It also warns that the Gateway process is still not taken seriously enough by departments, with the same issues and shortcomings repeatedly highlighted by reviews, and projects still entering the process too late.
And even though the process is mandatory for high and medium risk projects, 30 per cent currently bypass gates zero and one, and the PAC said the Treasury should consider withholding funds from IT projects where departments consistently choose to ignore stages of the Gateway process, and in doing so increase the risks of project failure.
The report added: "This committee believes that, to further enhance external scrutiny, there is a strong case for the publication of Gateway review reports, particularly given the repeated failures of public sector IT-enabled projects and programmes in recent years."
GME brand retailers, field managers and internal departments to develop service request resolutions & action plans Escalating issues to the Team ...
Effectively communicate across functional areas and to executive management on project progress, issues and risks Identify key issues/roadblocks for ...
Develop and manage project governance including steering committee meetings, sponsor meetings, project team meetings, status reports, etc. Establish ...
Agenda Setters 2008
Welcome to the ninth annual Agenda Setters poll – silicon.com's list of the top 50 most influential individuals in the technology and IT industries, from techies and CIOs to entrepreneurs and business leaders. Find out more in our latest special report.
Stories from the web...
Copyright © 2008 CBS Interactive Limited. All rights reserved. Top of page
Mark McDonald CIOs: Go large for services The bigger the better
Stuart Packham Looking for a job? Look no further Five top recruitment trends